← Academy

Demonstrating delay: the longest path, evidenced

A delay claim must show completion moved, on the critical path, because of the event. Longest-path tracing, correlating events to windows, and handling concurrency without hand-waving.

Schedule · 6 min read · updated 2026-06-12 · FIDIC 2017 Red Book references unless stated

1. The question every tribunal asks

Strip the methodology debates away and a time claim must demonstrate three things: that completion moved; that it moved along the path that actually governs completion; and that the movement was caused by the event relied on. Most failed delay claims fail on the second and third — they prove lateness, not causation on the critical path.

2. Trace the longest path, not the loudest activity

The critical path is whatever chain of activities and logic actually drives the completion date — the longest path through the network — and it migrates as the project progresses. An activity with zero float in the baseline may be irrelevant by month six; the analysis must follow the path as it stood in each window, not as it was planned on day one.

Float behaviour is part of the story: an event that consumes float without moving completion is not (yet) critical delay — but it changes the project's resilience, and your contract or its PCs may say who owns that float.

In ControlsIQ
Delay Analysis traces the longest path through each uploaded programme natively, so the governing chain in each period is identified from the network itself — not asserted from a bar chart.

3. Correlate events to the windows where the path moved

Causation is shown by correlation in time and in logic: the event happened in this window; the path ran through the affected activities in that window; completion moved by this amount in the same window. That correlation is exactly what contemporaneous programme versions plus a maintained event log make demonstrable.

In ControlsIQ
Events logged in Notice Tracker correlate to the delay windows in the analysis — the same event record that carries the notice dates carries the delay attribution, so the contractual and forensic stories stay one story.

4. Concurrency: address it, don't bury it

Where an employer-risk and a contractor-risk delay overlap, say so, and state the treatment applied — whether the contract prescribes one (check the PCs), or you adopt a recognised approach and apply it consistently. An analysis that visibly engages with concurrency is more credible than one that pretends the overlap is not there — and credibility is the currency these analyses trade in.

5. Present the analysis so it can be checked

Show the network versions used, the windows, the path in each window, the events mapped to each movement, and the arithmetic from movement to EOT claimed. The reader who can verify each step is a reader who can grant the claim — the same principle that governs the claim submission itself.

In ControlsIQ
The analysis, the programme comparisons and the event log export together — a verifiable bundle from baseline to claimed entitlement.
Run this workflow — freeSee the platform

Educational content for construction professionals. This guide summarises common contract mechanics and industry practice; it is not legal advice, and contract forms differ — your contract’s wording, including its Particular Conditions, governs. ControlsIQ outputs are designed to support professional judgement, not replace it.